![]() The resource calendar can affect the scheduling of a resource-driven task but not a fixed duration task. Is there a resource assigned to the task? To check a summary task for predecessors or constraints, follow these steps: If a Summary task (at any level) has a predecessor or a constraint, the subtask cannot be scheduled any earlier than the summary task. If the Task Delay field contains a value greater than zero, you cannot schedule the task earlier. Is there a value in the Task Delay field? To set resource leveling to manual, select Leveling Options on the Resource tab, and then select Manual. To remove delay, select Clear Leveling on the Resource tab. To remove any delay added to a task and to set resource leveling to manual, do the following: If you select the manual option, delay will not be added to tasks automatically. This results in the task Start Date being pushed out.